A SYSTEMATIC APPROACH TO PROVE DISRUPTION AND DELAY IN MEGA PROJECTS
Khaled Ahmed Ali Alnaas;
Abstract
Usually construction projects face disruptions and delays, especially in
mega/complex projects with many interfaces. The term “delay and disruption”
is used when claims are made for delays and cost overruns on complex projects
and there have been difficulties in justifying and quantifying such claims.
Disruptions and Delays can cause serious consequences to any project.
However, the nature of disruption is still not fully understood. The aim of this
research is to discuss the issues and difficulties in gaining a full understanding.
In particular, it presents various ways in which disruptions occur, and the
consequences that may occur. It, also, focuses attention on a number of issues
that arise when normal methods of analysis of mega (complex) projects are
used.
The main objectives of the this research are to; (1) assess the awareness of the
different parties involved in the construction industry about the disruption
concept, (2) explain the different available methods to justify and quantify the
delay and disruption, (3) provide a guideline for preparing comprehensive
extension of time (EoT) claim. This would be beneficial for the contractor to
prepare a well supported claim and for the employer to know what is required to
assess EoT claims, 4) identify the advantages and disadvantages of global
disruption claims by introducing a case for global disruption claim, and finally
5) develop change management control system (CMCS) as a tool that will assist
the contractor to prove disruption and make the process of preparation,
reviewing and approval much faster.
Keywords: Delay, concurrent delay, disruption, extension of time (EoT),
change, change management, claims, entitlement, earned value, recording
disruption, time at large, and float.
mega/complex projects with many interfaces. The term “delay and disruption”
is used when claims are made for delays and cost overruns on complex projects
and there have been difficulties in justifying and quantifying such claims.
Disruptions and Delays can cause serious consequences to any project.
However, the nature of disruption is still not fully understood. The aim of this
research is to discuss the issues and difficulties in gaining a full understanding.
In particular, it presents various ways in which disruptions occur, and the
consequences that may occur. It, also, focuses attention on a number of issues
that arise when normal methods of analysis of mega (complex) projects are
used.
The main objectives of the this research are to; (1) assess the awareness of the
different parties involved in the construction industry about the disruption
concept, (2) explain the different available methods to justify and quantify the
delay and disruption, (3) provide a guideline for preparing comprehensive
extension of time (EoT) claim. This would be beneficial for the contractor to
prepare a well supported claim and for the employer to know what is required to
assess EoT claims, 4) identify the advantages and disadvantages of global
disruption claims by introducing a case for global disruption claim, and finally
5) develop change management control system (CMCS) as a tool that will assist
the contractor to prove disruption and make the process of preparation,
reviewing and approval much faster.
Keywords: Delay, concurrent delay, disruption, extension of time (EoT),
change, change management, claims, entitlement, earned value, recording
disruption, time at large, and float.
Other data
| Title | A SYSTEMATIC APPROACH TO PROVE DISRUPTION AND DELAY IN MEGA PROJECTS | Other Titles | اسلوب منهجى لاثبات التعطيل والتاخير فى المشروعات العنلاقه | Authors | Khaled Ahmed Ali Alnaas | Issue Date | 2014 |
Recommend this item
Similar Items from Core Recommender Database
Items in Ain Shams Scholar are protected by copyright, with all rights reserved, unless otherwise indicated.