ENERGY AND AVAILABILITY ANALYSIS OF THE STEAM POWER PLANTS CASE STUDY: ABU QIR POWER PLANT UNIT 5

Mohamed Sherif Ahmed Ahmed Rabie;

Abstract


In this study, An energy and exergy analysis were made on the Abu Qir power plant unit 5 in Alexandria, Egypt to measure the performance of the unit and to identify the plant components that have the largest amounts of losses.
The analysis was made on the loads 277 MW, 260 MW, 233 MW and it is compared with the design load . The largest amount of exergy destruction was found at the load of 277 MW where the highest exergy destruction was found in the boiler which destroyed 405.6 MW. It is followed by the turbine where 66.3 MW was lost to the environment. The condenser was the third highest source of irreversibility with a value of 13 MW. The 1st and 2nd law net efficiencies in this case were 37.54% & and 35.41% respectively.
In addition, The exergy efficiency of the turbine and boiler decreased when the environment temperature raised (as in the summer) while the condenser efficiency increased. Each decrease in the intermediate turbine steam inlet temperature by 10 degrees will cause the unit load to decrease by 5 MW and the thermal efficiency by 0.73%. Also, each raise in the condenser pressure by 0.01 bar, the unit load decrease by 0.7 MW and the thermal efficiency drop by 0.8%.


Other data

Title ENERGY AND AVAILABILITY ANALYSIS OF THE STEAM POWER PLANTS CASE STUDY: ABU QIR POWER PLANT UNIT 5
Other Titles تحليل الطاقة و الإتاحية لمحطات القوى البخارية دراسة حالة : محطة كهرباء أبو قير الوحدة الخامسة
Authors Mohamed Sherif Ahmed Ahmed Rabie
Issue Date 2020

Attached Files

File SizeFormat
BB483.pdf502.83 kBAdobe PDFView/Open
Recommend this item

Similar Items from Core Recommender Database

Google ScholarTM

Check

views 8 in Shams Scholar
downloads 2 in Shams Scholar


Items in Ain Shams Scholar are protected by copyright, with all rights reserved, unless otherwise indicated.