Genetic Algorithm for Project Scheduling and Resource Allocation under Uncertainty

Fady Safwat Labib;

Abstract


The objective of the present work is to construct a mathematical model to solve the problem of project scheduling and allocation of resources under uncertainty in duration and resource requirements of individual tasks. The model is composed of an objective function which maximizes the probability of success to complete the project in a given time window and a set of constraints that satisfy the precedence relationships and the resource constraints. The proposed model considers the non-availability of the total number of resources from the beginning of the project.
A Genetic Algorithm is developed to solve the proposed model, and a visual basic program under Excel was written to solve the Genetic Algorithm.
The proposed model was validated through two case studies of different sizes (number of activities). The proposed approach proved to be efficient in solving the problem and realizes better solution than other approaches found in the literature, especially the models based on non linear optimization.
Keywords: Project Management and Scheduling, Resource-Constraints, Genetic Algorithms, uncertainty.


Other data

Title Genetic Algorithm for Project Scheduling and Resource Allocation under Uncertainty
Other Titles استخدام الخوارزمات الجينية فى دراسة جدولة المشروعات و تخصيص الموارد فى ظل وجود اللايقينية
Authors Fady Safwat Labib
Issue Date 2016

Attached Files

File SizeFormat
G13613.pdf760.04 kBAdobe PDFView/Open
Recommend this item

Similar Items from Core Recommender Database

Google ScholarTM

Check

views 2 in Shams Scholar


Items in Ain Shams Scholar are protected by copyright, with all rights reserved, unless otherwise indicated.