Managing Design and Implementation of Curtain Walls for High Rise Buildings
Doaa Mohamed Fathy Ahmed Badr;
Abstract
Finishing the installation of the curtain walls through successive phases (design,
manufacturing, implementation, maintenance) and each phase affected by the
previous phases. Lack of communication between stakeholders (architect, consultant,
structural engineer, client, faced engineer, manufacturing officials, contractor) leads to
conflicting information leading to failure of curtain walls.
Problems in many curtain walls in the design, manufacture and implementation
phases resulting from the absence of a framework that helps the project manager to
make the appropriate decision when designing and implementing curtain walls.
The thesis deals with the study of the design phase and the implementation
phase of the curtain walls and the factors affecting the performance of the curtain walls
to try to reach a frame that helps the architect in making the design decisions and
assisting the project manager in the implementation of the curtain walls to improve the
performance of curtain walls by reviewing literature and analyzing case studies and
interviewing engineers with experience in designing and implementing facades.
During the design phase, the curtain wall system is chosen according to the cost,
quality, performance and appearance. The environmental conditions, the location of
the project and the built-in orientation should be studied. The use of the checklist helps
the designer achieve the performance requirements of the curtain walls , Wind
resistance, air leakage resistance, water leak resistance, fire resistance, curtain wall
maintenance and access). Checking and documenting the materials used for the curtain
walls not only facilitates the work during the design phase, but also helps to improve
the performance at all phases.
Organizing the site and setting a timetable for the implementation of the tasks of
installation, documentation and control of the work from the delivery of parts of
curtain walls to the site until the completion of installation leads to the success of the
implementation phase. For each system has the special installation method
recommended by the manufacturer to ensure the quality and safety of installation.
Any defect during the installation may lead to the failure of the system such as a
complete leakage of water, air leakage and glass breaking resulting from the expansion
of aluminum. The use of checklist during the implementation phase of the curtain walls
helps to follow the progress of the work during the implementation phase, as well as
the confirmation of receipt of all the necessary drawings to install and confirm the
implementation as the required form in order to provide a suitable faced for building
and capable of the following performance requirements:
manufacturing, implementation, maintenance) and each phase affected by the
previous phases. Lack of communication between stakeholders (architect, consultant,
structural engineer, client, faced engineer, manufacturing officials, contractor) leads to
conflicting information leading to failure of curtain walls.
Problems in many curtain walls in the design, manufacture and implementation
phases resulting from the absence of a framework that helps the project manager to
make the appropriate decision when designing and implementing curtain walls.
The thesis deals with the study of the design phase and the implementation
phase of the curtain walls and the factors affecting the performance of the curtain walls
to try to reach a frame that helps the architect in making the design decisions and
assisting the project manager in the implementation of the curtain walls to improve the
performance of curtain walls by reviewing literature and analyzing case studies and
interviewing engineers with experience in designing and implementing facades.
During the design phase, the curtain wall system is chosen according to the cost,
quality, performance and appearance. The environmental conditions, the location of
the project and the built-in orientation should be studied. The use of the checklist helps
the designer achieve the performance requirements of the curtain walls , Wind
resistance, air leakage resistance, water leak resistance, fire resistance, curtain wall
maintenance and access). Checking and documenting the materials used for the curtain
walls not only facilitates the work during the design phase, but also helps to improve
the performance at all phases.
Organizing the site and setting a timetable for the implementation of the tasks of
installation, documentation and control of the work from the delivery of parts of
curtain walls to the site until the completion of installation leads to the success of the
implementation phase. For each system has the special installation method
recommended by the manufacturer to ensure the quality and safety of installation.
Any defect during the installation may lead to the failure of the system such as a
complete leakage of water, air leakage and glass breaking resulting from the expansion
of aluminum. The use of checklist during the implementation phase of the curtain walls
helps to follow the progress of the work during the implementation phase, as well as
the confirmation of receipt of all the necessary drawings to install and confirm the
implementation as the required form in order to provide a suitable faced for building
and capable of the following performance requirements:
Other data
| Title | Managing Design and Implementation of Curtain Walls for High Rise Buildings | Other Titles | إطار مقترح لإدارة أعمال التصميم والتنفيذ للحوائط الزجاجية للمباني المرتفعة | Authors | Doaa Mohamed Fathy Ahmed Badr | Issue Date | 2019 |
Attached Files
| File | Size | Format | |
|---|---|---|---|
| CC2514.pdf | 730.01 kB | Adobe PDF | View/Open |
Similar Items from Core Recommender Database
Items in Ain Shams Scholar are protected by copyright, with all rights reserved, unless otherwise indicated.